Dock Master Program (Oakridge Mall)
A comprehensive Construction Management initiative ensuring seamless logistics and operations for the Oakridge Mall redevelopment.
About the Program
The Dock Master Program for the Oakridge Mall redevelopment is a structured Construction Management initiative that oversees and facilitates the smooth execution of Phase 1 of the Oakridge Mall Redevelopment Dock Master Operation Program. This program includes all necessary supervision, labor, materials, equipment, and services required to efficiently execute and complete the project.
Oakridge Mall will be home to a curated selection of world-renowned luxury brands, including Louis Vuitton, Prada, Brunello Cucinelli, Moncler, Versace, Max Mara, Maison Margiela, Miu Miu, Christian Louboutin, Alexander Wang, Tiffany & Co., Bvlgari, and Rolex.
 
															 
															Scope of Work
					 1. Temporary Site Offices & First Aid Facilities 
							
			
			
		
						
				- Provision and installation of site offices, tool storage, and first aid stations to support project execution.
- Meeting spaces for mall ownership, consultants, and project teams.
					 2. Resource & Labor Management 
							
			
			
		
						
				- Coordination and allocation of skilled personnel and resources.
- Oversight to ensure seamless implementation of the dock master program.
					 3. Temporary Facilities 
							
			
			
		
						
				- Setup of temporary restrooms and waste control systems for tenant improvement contractors.
					 4. Program Execution 
							
			
			
		
						
				- Logistics Package Development – Mobilization of The Bay, Sobeys, and the Bike Silo.
- Pre-Mobilization & Delivery Logistics – Coordination for anchor tenants.
- Dock Master Program & Delivery Logistics – Management of CRU tenants.
Management Team
						
							Project  
Manager						
					
				
				
			
						
							Project 
 Coordinator						
					
				
				
			
						
							Safety Manager / 
 Safety Inspector						
					
				
				
			
						
							Safety 
 Coordinator						
					
				
				
			
						
							Construction  
Accountant						
					
				
				
			
						
							North Zone 
 Dock Master (1)						
					
				
				
			
						
							South Zone
 Dock Master (2)						
					
				
				
			
						
							Middle Zone 
 Dock Master (3)						
					
				
				
			
						
							Labor 
Foreman						
					
				
				
			 
															 
															Manpower Resources (Per Zone)
1
Delivery 
Attendant
				3
Hoist 
Operators
				2
General
Laborers
				4
Heavy Equipment
 Operators
				Additional Responsibilities Included in the Program
- First Aid Supplies
- Bobcat Rentals
- Trucks
- Trolleys & Power Jacks
- Directional Signage System for Tenant Improvement (T.I.)
- Communication System – Walkie-Talkies for field personnel operations
- Hoist Communication Setup at Section 5 Elevator
- Temporary Restroom Setup
- Gates & Gantries Installation
- Attendance Booths (3)
- Remote Security Cameras
- Office Supplies & Equipment
- Printing & Reproduction Services
- Tools & Equipment
- Additional Water Supply Arrangements for Tenant Improvement Contractors
- Additional Power Supply Arrangements for Tenant Improvement Contractors
- Access Protection Measures for Tenant Improvement Contractors
 
											 
											 
											 
											 
											 
											 
											 
											 
											 
											